January 2024
The Oldminster enabling projects are still on hold pending Canal & River Trust (CRT) Easement agreement. We are working on further costings to help with grant funding applications and the haul road project. The planning application for the new shed is progressing:-the Environmental Case is currently being updated. Work started on documentation needed for the new Shed design and construction tendering, and on Construction Design Management (CDM) documents for the Leyhill workforce trackwork training. Meanwhile, at the Sidings, we have completed work on the hard standing and triangle (which provide vehicle access to the site) and we are now working on erecting the fencing. We have also purchased an excavator!