September 2023
The Oldminster enabling projects are progressing well, but the next steps are being delayed by the lack of CRT Agreements on access and easement, although easement work appears to be progressing.
The site drawings are being reviewed again to include a southern access and road suitable for future railway vehicle deliveries. Programme plans have been progressed and will also be reviewed. The planning application for the new Shed is in its final stages, ready for submission.
Over the next month, we will be reviewing activity and resource plans, establishing costs for mechanised dead hedge clearance to enable fencing work and making proposals for moving out of the Old Shed. We will also continue work on costings for water, sewerage and electricity.